Projects

TECAN is developing an expansion project through the conversion of its power plant from OCGT to a CCGT, which will increase its installed capacity by 252 MW, from 324 MW to 566 MW, which represents a boost in its capacity of close to 80%. This installed capacity increase will represent an expansion of approximately 19.8% of our total installed capacity and will allow TECAN to receive incremental OEFs through additional Reliability Charge revenues that were assigned through the auction that took place on February 28, 2019.  As a CCGT, TECAN will become more efficient by reducing its heat rate to approximately 6,618 BTU/KWh, representing an efficiency enhancement of 35% (from 10,219 BTU/KWh under its current OCGT configuration).

Project Progress

95.2%

Completed Milestones

Milestone 1    Advanced Payment

Milestone 3    Steam Turbine Generator Turbine Ordered

Milestone 8    Award Geothecnical Study Subcontract

Milestone 4    Award PO for HRSGs

Milestone 7    Award PO for Bypass Stacks

Milestone 14    Award PO for Air Colled Condenser

Milestone 17    Award PO for Generator Step-Up (GSSU) and auxiliary Transformers

Milestone 67    All Fuel Gas Piping Installed Tested, Flushed and Cleaned

Milestone 36  HRSG1 Foundations Complete

Milestone 40  HRSG2 Foundations Complete

Milestone 38  Initial Piperack Steel Delivery CIF

Milestone 42  Steam Turbine Generator Delivery FOB

Milestone 50  Steam Turbine Generator Delivery to site

Milestone  58  HRSG1 Heavy Module Erection Manouver Complete

Milestone  66  HRSG1 Set HP, IP, and LP drums

Milestone  61  HRSG2 Heavy Module Erection Manouver Complete

Milestone  63  Firewater Storage Tank Complete

Milestone  73  HRSG2 Set HP, IP, and LP drums

Milestone 48  STG Lower Casing Set and aligned

Milestone 59 Gas Regulating and Metering Station Delivery Complete to site

Milestone 65 Generator Circuit Delivery Complete to site

Milestone 70 Feedwater Complete to site

Milestone 79 220v Sus Energized

Milestone 77 Delivery of Steam Bypass Valce to site

Milestone 43 Admin Building foundation execution: Formwork Completed

Milestone 78 CEMS House placed on Foundations Complete